Open side-bar Menu
 3DEXPERIENCE Construction

Archive for September, 2014

Spotlight on Becher Neme: BIM Expert Pushes a Zero-Change-Order Approach

Thursday, September 25th, 2014

 

The team that makes up Neme Design Solutions, a Long Beach, California-based BIM consultancy, specializes in simplifying highly complex projects to enable fabrication.

Led by founder Becher Neme, the firm includes a small team of architects and engineers with more than a decade of experience working onsite with general contractors, and with particular expertise in the CATIA solution.

This combination of field experience and software knowledge has helped the firm carve out a unique niche in model clash detection and resolving interface challenges.

(more…)

Flip the Script: Ask Planning Questions in This Order for Better Project Outcomes

Thursday, September 18th, 2014

 

AEC Planning Questions

When architects and planners work with owners, they usually accept a proposed site and think about how to arrange and orient a building on that site. They develop ideas about what the building should look like in some detail before engaging builders or construction managers in ideas about how the building will be delivered.

Then, if the project cost cannot be brought in line with the budget, another site or an existing building renovation is considered.

AEC teams tend to think first about what to build, then how to build, and finally where else they should think about building.

(more…)

How Lean Construction Practices Are Decreasing Schedules for Contractors

Thursday, September 11th, 2014

 

McGraw Hill Construction, the Lean Construction Institute, and Dassault Systèmes teamed up to produce an in-depth report on Lean Construction. Below is an excerpt from that report on the the impact Lean practices are having on contractors in regards to scheduling.


The Impact on Contractors of Schedule Decreases Due to the Adoption of Lean Practices

impact on contractors scheduleReduced project schedule is one of the top benefits of adopting Lean practices, and saving time in the construction industry also cuts costs on projects and can increase profitability.

However, the savings only accrue to the contractor if the owner has not already factored the reduced amount of time into their expectations of the contractor, especially in the case of a negotiated project, or if the contractor has not deemed it necessary to build those cost savings into their bid in order to win a project in a highly competitive market.

The study results suggest, though, that these options are not mutually exclusive. About two thirds of contractors report that the schedule savings they experience due to their Lean practices do have a positive impact on the profit they experience in their projects, and just about the same percentage of contractors report that they are able to bid projects more competitively due to the schedule savings.

Tweet: About 2/3 of contractors report that adoption of #LeanCon allowed them to bid more competitively @Dassault3DS http://ctt.ec/eyEIi+Tweet: “About 2/3 of contractors report that adoption of #LeanCon allowed them to bid more competitively”

Clearly, there must be significant overlap of firms who both have schedule reductions feeding their bottom line and schedule reductions absorbed in their efforts to be more competitive.

However, the findings also reveal that the industry is nearly unanimous about the growing expectations of owners that projects can be done in shorter time frames due to the adoption of Lean practices in the industry.

Tweet: The industry expects that projects can be done in shorter time frames due to the adoption of #LeanCon @Dassault3DS http://ctt.ec/8XBEi+Tweet: “The industry expects that projects can be done in shorter time frames due to the adoption of #LeanCon”

(more…)

Façade Design and Fabrication: The Expensive Disconnection

Thursday, September 4th, 2014
 

facade3

Most BIM technologies today disconnect the production of permit drawings from the processes for fabrication and installation. When owners include subcontractors in preconstruction services (as they often do with general contractors) they have the ability to coordinate these activities and reduce errors.

What is needed then is a data backbone to connect the building design to the fabrication detailing and installation sequences. It is common practice to have architects design a façade, independently from the manufacturer who fabricates the façade, and also independently from the general contractor and subcontractors who install the façade system.

(more…)




© 2024 Internet Business Systems, Inc.
670 Aberdeen Way, Milpitas, CA 95035
+1 (408) 882-6554 — Contact Us, or visit our other sites:
TechJobsCafe - Technical Jobs and Resumes EDACafe - Electronic Design Automation GISCafe - Geographical Information Services  MCADCafe - Mechanical Design and Engineering ShareCG - Share Computer Graphic (CG) Animation, 3D Art and 3D Models
  Privacy PolicyAdvertise