Puuvilla Shopping Centre in Pori, Finland by Arkkitehtikonttori Küttner & Pussinen Oy

 
April 23rd, 2014 by Sumit Singhal

Article source: Tekla 

Shopping center Puuvilla is founded on piles. The frame is built with reinforced concrete pillars, hollow-core and cast-in-place slabs and pre-stressed concrete beams, with interconnecting steel pillars and beams on the Kutomo end.

Structural design and precast detailing is done by modeling and steel roof structures and facade elements are modeled with Tekla.

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

  • Architects: Arkkitehtikonttori Küttner & Pussinen Oy
  • Project: Puuvilla Shopping Centre
  • Location: Pori, Finland
  • Project group: Skanska, Renor Oy, Ilmarinen, Arkkitehtikonttori Küttner & Pussinen Oy, Narmaplan Oy,
  • Project Team: Oy, Firecon Group Oy, A-Insinöörit Oy, Parma Oy, Beam-Net Oy, Contria Oy, TPE Turun Pelti ja Eristys Oy, FMC Group

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Architectural, MEP, electricity, and sprinkler design is done by modeling and the existing structures are laser scanned and an inventory model is created.

Special feature in this project is the very tight element erection schedule and combining new and preserved structures.

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Challenges

The team experiences several challenges.

General challenges:

  • Great number of project parties
  • Large project
  • Tight schedule
  • Structural combining of new and old structures, nearness of the river Kokemäenjoki and ground circumstances.

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Modeling challenges

  • Phasing planning, design and modeling, delivery of initial information
  • Large size of models
  • Model upgrading frequency

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Success factors

The frame phase is  nearing its end and the project has progressed according to plans. Element installations have progressed at record speed considering the size of the project and the planned schedule. This has been made possible by BIM, design by modeling and flawless design and detailing. Models by other disciplines have been utilized in design and MEP installations have started.

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

In regard to future projects and development it is certainly essential to plan the design phasing to better support BIM. This development is mainly focusing on the process and not necessarily on the technical tools. The current BIM tools make efficient process possible, but design by modeling needs more initial information than traditional design. This is exceptionally challenging in premises projects where essential decisions from design point of view may stay open until very late in the project.

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Image Courtesy © Arkkitehtikonttori Küttner & Pussinen Oy

Category: shopping center




© 2024 Internet Business Systems, Inc.
670 Aberdeen Way, Milpitas, CA 95035
+1 (408) 882-6554 — Contact Us, or visit our other sites:
TechJobsCafe - Technical Jobs and Resumes EDACafe - Electronic Design Automation GISCafe - Geographical Information Services  MCADCafe - Mechanical Design and Engineering ShareCG - Share Computer Graphic (CG) Animation, 3D Art and 3D Models
  Privacy PolicyAdvertise