Article source: BURO II & ARCHI+I
In an ingenious way – the introduction of a ‘light street’ – this renovation project adds new life, light and space to this deep and dark former offi ce building. This indoor street is the walkway for all reception functions, as well as the supporting element of this energetic concept.
- Architects: BURO II & ARCHI+I
- Project: ADMINISTRATIVE CENTRE
- Location: ZWEVEGEM, Belgium
- Photography: Klaas Verdru
- Client: Municipal Zwevegem
Team
- EXÉCUTION: SILEGHEM & PARTNERS
- ECOLOGICAL ASPECT: ESTER
- Project director: Claude Labeeuw
- Design architect: Arch. Steven Vanwildemeersch
- Interior architect: Int. arch. Bart Decloedt
Status
- Specified execution term: implementation by Sileghem & Partners
- Actual execution term: implementation by Sileghem & Partners
Surfaces
- Area surface: Land use of the building:
- Gross floor area: 5.262 m²
Energy Performance [EPB]
- E level: E30 – K level: K24
FINANCIAL DATA
- Originally estimated budget: € 3.758.491,75
- Contracted budget: € 5 678 645,23
Contractors
- Closed shell construction: Detrac nv
- Walls, ceilings and interior joinery: Bekaert Building Company nv
- Floors, chape and patch work: Dé-bouw nv
- Fixed furniture: De Grande Projects nv
- Sanitary, HVAC: Develtere Chauffage nv
- Electricity and data: Bryon nv
- Lifts: Coopman Liften nv
- Painting, curtains and signalisation: Van De Kerkhof bvba
- Surroundings: Tuinen Descamps bvba